Eastern Shore Public Library Parksley

The Eastern Shore Public Library’s completion will have to wait a few more months.

Due to difficulties in obtaining building materials related to the COVID-19 epidemic, RH Contracting, the General Contractor for the Eastern Shore Regional Library Project has requested a four month extension for the completion of the project.  The original deadline for completion was December 13, 2020. 

The new date of completion is now April 13, 2021.

The contract calls for liquidated damages of $1,500 per day after the completion deadline. The Board of Supervisors voted for the liquidated damages to be deducted until December 31, which would allow the contractor to retain the services of the architectural firm that supervises the project until April 13. 

YMCA Find Your Groove, Join Today!

The Board of Supervisors voted unanimously to approve the extension.

.

Alexa Coastal Country 300

Share this

Listen Live!

WESR 103.3FM PLAY BUTTON
COASTAL COUNTRY PLAY BUTTON

Local Weather

April 28, 2024, 3:46 pm
Broken clouds
WSW
Broken clouds
73°F
7 mph
Apparent: 73°F
Pressure: 1021 mb
Humidity: 61%
Winds: 7 mph WSW
Windgusts: 29 mph
UV-Index: 6.2
Sunrise: 6:10 am
Sunset: 7:50 pm
 

Visit our sponsors

FOLLOW US

OUR ADVERTISERS

Buchanan Subaru

Member of the

esva chamber